Foundation Repair & Renovation Progress Update

Things have been moving along slowly but surely. The foundation has finally been leveled and they are pouring the concrete on Monday. They plan to be done by the end of next week! It's already incredibly different inside the house, particularly in the kitchen where it no longer feels like you are climbing up a hill to get to the sink.

As they leveled the section of the house that the previous owners added on, the whole addition began to separate from the main house. This isn't surprising considering everything the previous owners did on the house was done as haphazardly as possible (remember the "wall use only" boards glued to the efficiency apartment floor?). This is kinda freaky and tbh, i'm not sure what exactly we are going to have to do to fix that. More learning to do.


IMG_6825.jpg
IMG_6826.PNG

Once foundation is done it will be time for a whole new roof! ...and electrical!...and plumbing! :) The foundation contractors found a leak behind the shower wall in the main house so we will need to get that taken care of asap. And once the electrical is fixed, hopefully the a/c will work!

One major layout decision we are trying to make involves the center bedroom that has no windows. We know we are going to take it down to open up the main living space, but we also would like to use part of it to put in a second bathroom. Also, the entire back of the house is currently bedrooms, none of which have a door to the exterior. The front door is currently the only entrance/exit. With smaller bedrooms, it's hard to figure out where it makes the most sense to put in a door. Luckily, we've been getting some professional help on these decisions -shout out to our wonderful friend and architect Jelisa for helping us figure it all out. 

That's it for now. We promised a full house tour and failed miserably at delivering that, but I remain hopeful we will get that up next week.

-Em O